    June Pre-construction
  • 2
    Week 2 – July 19 – Foundations
  • 3
    Week 6 – August 16 – Underground
  • 4
    Week 7 – August 23 – Backfill
  • 5
    Week 9 – September 6 – Steel Erection
  • 6
    Week 10 – September 13 – Steel/Masonry
  • 7
    Week 12 – September 27 – Concrete/Roofing
  • 8
    Week 14 – October 11 – Complete Sales Floor Slabs
  • 9
    Week 18 – November 8 – Exterior Finishes
  • 10
    Week 23 – December 13 – Shelving Installation
  • 11
    Week 26 – January 3 – Construction Complete