June Pre-construction
Week 2 – July 19 – Foundations
Week 6 – August 16 – Underground
Week 7 – August 23 – Backfill
Week 9 – September 6 – Steel Erection
Week 10 – September 13 – Steel/Masonry
Week 12 – September 27 – Concrete/Roofing
Week 14 – October 11 – Complete Sales Floor Slabs
Week 18 – November 8 – Exterior Finishes
Week 23 – December 13 – Shelving Installation
Week 26 – January 3 – Construction Complete